Gaining Traction: Water Quality, Habitat & Public Health

Located in a mostly-agricultural area outside of Gaston, within the approved boundaries of Wapato Lake National Wildlife Refuge, Spring Hill Natural Area is one of the latest links in a growing chain of ecological enhancement projects in the Wapato Lake-to-Fernhill wildlife corridor.

Spring Hill Natural Area consists of a north parcel and a south parcel, with one privately-owned tree nursery in between. Most of the acreage lies within the active floodplain, and much of it remains underwater during the rainy season. The natural area is located in the northern part of the once-vast Wapato Lake peat wetland. The site sits across the road from Fernhill Forest, across the Tualatin River from Hutchinson, and roughly equidistant from Wapato Lake and Fernhill. Two miles downriver, the Spring Hill Pump Station draws the majority of the county’s drinking water from the Tualatin River.

Five creeks (Harris, Fern Hill, Wapato, Scoggins, and an unnamed tributary) touch the site, as does the main stem of the Tualatin. For decades, much of the creek water of the northern parcel at Spring Hill disappeared underground into a drainage system that made agricultural activities more efficient. In the summer of 2018, after removing a small dam, contaminated soil that disconnected wetlands, and roughly 4,000 semi-truck tires that served as the makeshift drainage system, crews created more natural flow paths for two seasonal creeks and placed large wood to improve stream and wetland functions. Cattle grazing continues at the site, as does farming of tall fescue, clover and wheat.

Today, Spring Hill Natural Area functions as both productive working land and a showcase of ecological enhancement strategies.


The Site

First planting: 2018
Size: 246 acres
Stream length: 1.4 miles
Plant communities: Riparian Forest, Shrub and Emergent Wetlands, Prairie

 

The Challenge

Doing ecological enhancement at sites after decades of heavy human use always presents challenges. Here, as is common, partners encountered invasive plants, sparse riparian vegetation, and ditched and tiled creeks.

The unique element that members of Spring Hill’s project team will always remember involved the drainage system. It’s not unusual to find drain tiles at agricultural sites, typically made out of perforated pipe. Here, however, partners found long lines of buried semi-truck tires, arranged like beads on a string.

Prior to the project’s launch, the team knew that this repurposed-tire drainage system was in place in two locations on the property. When excavators got to work, to their surprise, they found double lines of tires in each location—in all, approximately 4,000 tires.

It wasn’t easy to find a tire disposal service with the capacity to handle such a big quantity of big tires responsibly. Ultimately, about half the project budget went to disposal—not only the tires, but also soil contaminated with hydrocarbons and pesticides, and debris from the small dam, or weir, at the farm pond.

 

The Transformation

In 2015, Metro purchased the property and began the process of removing several structures—a house, two outbuildings, and a silo. An attractive and historic Dutch gambrel barn is the only surviving structure.

The following year, the project team—including staff from Metro and Clean Water Services, as well as contractors—continued the multiyear process of preparing a site for revegetation, and they began to develop the ecological enhancement plan. 

By the summer of 2018, the team was ready to break ground and take advantage of the in-water work window: the dry season (mid-July to September in this watershed), when it’s possible to complete construction projects that involve stream and wetland work. At Spring Hill, these activities included removing contaminated soil, buried tires, and the farm pond dam; excavating meandering creek channels; and installing native sedge/rush mats, and large woody debris in those channels, to slow and clean the water while creating habitat. Revegetation of the newly constructed channels began with the application of hydroseed mix embedded with native grass and wildflower seed, to be followed soon by installation of thousands of bare-root native shrubs.

This fall, for the first rainy season in decades, two creeks at Spring Hill traveled aboveground, following slow and curving channels on their way to the Tualatin River. As the river swelled, now it met a reconnected floodplain free of impediments. Conditions were in place for the return of the rare prairie habitat believed to have been present at the site centuries ago, along with shrub and emergent wetlands and riparian forest.

With the big construction push behind them—and the mountain of tires finally gone—partners prepared for the next steps: continued vegetation management; site monitoring and adjustment; ongoing coordination with the holders of the farming and grazing leases; and moving on to the next project, the next piece in the growing network of large-scale landscape restoration efforts in the Tualatin River Watershed.


 

KEY PARTNERS